Prepare Documentation Before the Vessel Arrives
Before a used rig reaches port, begin preparing the commissioning documents. The destination team should request the packing list shipped with the machine, available drawings of dismantled parts and functional records to check removed guards, drill rods and battery status. Before lifting heavy assemblies, verify the relevant weights and work to the applicable lifting plan.
Collect the seller’s pre-shipment photos and GLOBMACH equipment records corresponding to the stock ID as material for comparison with the condition on arrival. Cross-check hours, service history and known faults against available documentation, and retain any uncertainty when records are insufficient. Manufacturer specifications describe a model’s configuration, not the condition of this particular used machine. If pre-shipment functional records are available, also confirm that they relate to the machine and identify the test conditions.
Lifting Plan and Weight Verification
Before the vessel arrives, have qualified personnel prepare a lifting plan for the actual transport configuration. Check each load’s weight, centre of gravity and lifting points, the load capacity of the rigging, and the crane load chart at the intended radius. Cross-check identification and weights with the packing list, dismantled-component drawings and equipment documents; verify unknown weights before lifting.
Keep the seller’s weight information with the shipping documents. If the information is insufficient, have qualified personnel verify the weight and lifting plan before the lift and confirm them under applicable site procedures.
Record the condition of the goods
On arrival, document the condition of the goods and packaging promptly under safe conditions. Where applicable, photograph the exterior before unloading or lifting, including close-ups of patches, dents or water marks. Record and report possible transport damage promptly to the relevant parties under the carriage contract and applicable procedures, keeping the photos and documents.
Check for possible transport damage or missing items, such as deformed lashing points, leaking hydraulic components, damaged cables and broken handrails. Record the issues and confirm repair arrangements, estimated costs and responsibility with the relevant parties; keep written records for commissioning and follow-up.
Check every item
Once the equipment is safely parked, check shipped dismantled parts, drilling tools, counterweights and guards against the packing list. Depending on the shipment, items may include drill rods, pulley blocks, guide rollers, batteries, charging equipment and a hydraulic power unit. Confirm the items against the actual machine and transport configuration, and record missing, damaged or inconsistent items. Where applicable, check counterweight and guard installation requirements in the equipment manual.
Missing counterweights or guards can affect equipment stability or personnel safety. Record missing or damaged items and have qualified personnel address them under the equipment manual before related operations.
Safe Assembly Sequence
Commissioning cannot simply be copied from one rig to another. Use the applicable manufacturer procedures for the specific model and transport configuration to determine support, lifting, assembly, hydraulic connection, guarding, interlocks and verification requirements. Before work begins, responsible qualified personnel should prepare a plan for the site conditions.
Prepare the required tools, approved torque data, lifting equipment, and qualified personnel according to the plan. If the correct manuals or engineering information are missing, pause assembly and obtain them from the supplier or manufacturer; do not substitute memory or procedures for similar models.
Static Inspection and No-Load Trial Run
After structural assembly, have qualified personnel use the manual and commissioning procedure for the specific machine and transport configuration to determine which fluid, transport-plug, filter and battery items need inspection, installation or replacement. Perform static checks with the equipment stationary and appropriate safeguards in place. Arrange any slewing or mast movement separately as a controlled operation under the manual and site safety conditions.
Qualified personnel should determine the no-load trial steps from the applicable manual, commissioning plan and equipment and site safety conditions. They may include winch, rotation and feed functions where fitted. Record the readings and abnormalities specified in the manual for comparison during applicable subsequent controlled-load testing and acceptance.
Controlled Load Test
Only where the specific model’s commissioning procedure and the machine and site safety conditions permit may qualified personnel carry out applicable load tests under an approved test plan using suitable tools or test equipment. Do not improvise suspended loads or reaction points. Record applicable readings, temperature trends, leaks and fault codes according to the manual and plan; if a pre-shipment baseline is available, compare the results with it, taking the agreed acceptance criteria into account.
Do not compress arrival, assembly and start of operations into a rushed job. Complete commissioning stages under the applicable procedures and record deviations, keeping an open-issues list with responsible persons and deadlines. If a leak or another issue occurs, qualified personnel should address it according to the manual and perform applicable rechecks. Whether operations can begin depends on the site requirements and acceptance results.
Open-issues list and final steps
The commissioning checklist can include open issues: deviations from the packing list, repairs completed, missing items and known related costs or delays. Assign responsibility and a deadline for each item and inform the project manager of unresolved issues.
Assembly, startup and pre-service acceptance should be completed by trained personnel according to the specific equipment manual, applicable local requirements and site plan. Review commissioning records and outstanding issues; when equipment and site safety conditions permit, perform the necessary controlled-load tests and complete acceptance under applicable procedures. For pre-arrival information on a specific machine, give GLOBMACH the stock ID and arrival port and request available commissioning records.








