Choose the shipping method based on the actual cargo
Used drilling rigs differ in dimensions, weight and transport configuration. A compact surface rig may suit a flat rack, while a heavy rotary piling rig may need another shipping arrangement; acceptance depends on the measured cargo, handling plan, vessel and ports. Compare flat rack, RoRo and breakbulk using the actual machine and transport pieces, not brochure dimensions alone.
The transport method affects the ports, vessel, handling equipment, securing plan and cost. RoRo can be considered for a rig that can drive and steer safely; cargo that cannot drive itself may also be rolled aboard on a trailer or other equipment accepted by the carrier. Compare flat rack and breakbulk against actual dimensions, weight and handling conditions as well, and measure the cargo and check the route and ports before deciding.
What a flat rack actually offers
A 40-foot flat rack is generally a platform without side walls or a roof and can carry some large or out-of-gauge cargo. Check whether the loaded cargo is out of gauge and the rack payload limit and securing plan, and whether the vessel and terminal accept the cargo for the specific rack, cargo and route. Securing must follow the loading and lashing plan confirmed by the relevant parties; fixed rack dimensions do not mean the loaded cargo occupies a fixed footprint.
Check the payload limits of the flat rack used and whether the carrier and terminal accept the cargo dimensions, centre of gravity and securing plan. A tall mast or high centre of gravity may require further assessment or another solution. Also confirm loading and unloading methods and the availability of suitable equipment at origin and destination.
RoRo: self-propelled cargo or handling equipment
RoRo means roll-on/roll-off and can be used for machines with suitable driving and steering capability; non-self-propelled cargo may also be rolled aboard on trailers or other equipment when accepted by the carrier. Confirm boarding, stowage and securing against the machine condition, vessel, terminal and accepted plan; loading onto a trailer or unloading may still involve lifting.
For self-driving or towing, check brakes, steering and operating conditions against carrier and terminal requirements. Equipment that cannot drive itself or has been partly dismantled is not automatically excluded from RoRo: ask whether a suitable roll trailer and associated handling plan can be used. In every case check the dimensions and loads of the actual cargo and loading equipment against the dimension and load limits of boarding ramps, other ramps and decks and port conditions.
Breakbulk: assess cargo pieces and handling conditions
Breakbulk may treat a rig or its parts as individual pieces of cargo, with handling dependent on the vessel, terminal and cargo. Some large rigs may need to be dismantled into pieces suitable for transport and lifting, while another accepted arrangement may be possible. Check each piece’s weight, dimensions, centre of gravity, appropriate lifting points and handling plan; do not assume every machine must be dismantled.
Breakbulk can offer more flexibility in individual piece size and weight, but handling and coordination requirements vary by plan. Prepare a detailed cargo list and an appropriate handling plan, and arrange reassembly at destination when dismantling is needed. Compare actual quotes for ocean freight, cranes, rigging, dunnage, lashing, inland transport and escort vehicles where needed, and confirm that the vessel or port has the required handling capability.
Compare the full cost of each option
The lowest ocean freight quote may not reflect the full cost when comparing flat rack, RoRo and breakbulk. Include dismantling and reassembly labour if a flat-rack plan needs them; an accepted roll trailer for non-self-propelled cargo may add handling or equipment costs. Check prices, constraints and risks for the actual transport plan.
Compare options that can safely accept the actual cargo and perform the agreed operations at the selected delivery endpoint. Include dismantling, lifting, protection, lashing, inland transport and reassembly as actually required and quoted, avoiding double counting; consider unquoted items and potential damage or delays as well.
What to measure before booking
Before contacting a forwarder, collect measured length, width, height and weight for each planned shipping piece and provide an available centre-of-gravity estimate. The transport survey should also identify appropriate lifting and lashing points and protrusions such as winches, pipes or handrails; general manufacturer specifications do not replace verification in the actual transport configuration.
State whether the rig can drive and steer safely and whether a trailer, lifting or another handling method is needed. For liquids, fuel and batteries, check declarations, securing and necessary treatment against the cargo, applicable regulations and carrier requirements; do not assume that draining is always required. If dismantling is planned, prepare the applicable drawings, hardware and reassembly information.
Check handling capacity at origin and destination ports
Check the route and the handling capability of the ports of departure and destination. A flat rack needs equipment suited to its actual loaded weight and dimensions; RoRo requires checks of vessel and shore ramps, berths, access and trailer conditions; for breakbulk check shore cranes, ship cranes or other handling equipment against the actual pieces and plan.
Before committing, request written confirmation from the carrier or forwarder that the origin and destination ports can accept the described cargo and plan, and check ramp dimensions, deck strength and securing conditions where necessary. The CTU Code jointly developed by IMO, ILO and UNECE provides guidance on packing and securing cargo transport units; it does not replace the specific carrier and terminal requirements and confirmations.
Anti-corrosion protection, lifting and lashing
Salt spray, rain, vibration and forces from lifting and lashing may damage hydraulic lines, electrical control cabinets, operator cabins and other areas. Determine packaging and protection according to the cargo, transport method and applicable requirements; assess anti-corrosion materials, desiccants and suitable physical protection as needed, without assuming every machine needs the same packaging.
Check lifting points and handling methods against each piece’s weight, centre of gravity and applicable information. A suitably competent person should develop a securing plan for the cargo, route and vessel under applicable requirements, with the relevant parties reviewing and confirming it according to their respective responsibilities.
What to Ask the Seller and Freight Forwarder
When you inquire about a used drilling rig on GLOBMACH, ask the seller for a measured shipping survey report for that exact stock unit, not just a model brochure. The survey report should include component weights, dimensions, center of gravity, lifting points, and a statement on whether the rig can drive and steer. Also ask for photos of each side of the rig and close-up photos of any damage or weak areas.
Give the forwarder the actual cargo information, compare feasible flat-rack, RoRo and breakbulk options for the route, and request an itemised quote to the selected delivery endpoint showing excluded and unquoted items. Ask the carrier for written confirmation that the cargo and handling plan are accepted and the relevant ports can handle them.
Your next step: request a quote for a specific stock item
When contacting GLOBMACH, state the stock number of the equipment you are interested in, the destination port, route options, number of cargo pieces, whether the machine can be operated, and the lifting capacity at the destination. Ask for the transport survey report, photos and shipping preparation instructions for that specific machine, then compare the flat-rack, RoRo and break-bulk options against the actual cargo and arrange booking.